Alternative Project Delivery: Progressive Design-Build and IPD

Public and private owners are increasingly moving away from traditional design-bid-build toward progressive design-build, construction manager at risk and integrated project delivery. The delivery model changes far more than the contract form: it changes when contractors are involved, how risk is shared, what engineers are responsible for and how design decisions get made. This briefing explains the main models and what they mean for engineering scope and risk.

Design-bid-build

In design-bid-build, the owner hires a designer to complete plans and specifications, then bids construction to contractors, usually awarding to the lowest responsive bidder. It offers clear separation of roles and price competition, but contractors are not involved in design, which can lead to constructability issues, change orders and adversarial relationships.

Engineers carry full responsibility for design completeness, and gaps or errors become change orders during construction.

It remains common for public projects because procurement rules favour competitive bidding and the process is well understood. For straightforward projects with stable scope, it can still deliver good value.

Construction manager at risk

Under CMAR, the owner hires a construction manager during design to provide preconstruction services such as estimating, constructability reviews and scheduling, then negotiates a guaranteed maximum price. Engineers remain under contract to the owner but collaborate with the CM, which can improve constructability and cost certainty.

A key engineering consideration is the timing of contractor involvement. Bringing the CM in early allows constructability input to shape design, while late involvement reduces value. Engineers should expect more frequent reviews and cost feedback during design.

Design-build

In traditional design-build, the owner contracts with a single entity for design and construction, often at a fixed price based on bridging documents or performance requirements. This shifts design risk to the design-builder, and engineers typically work for the contractor. It can speed delivery but reduces owner control over design details.

For engineers, working under a contractor changes priorities. Schedule pressure, cost targets and the contractor's means and methods shape design decisions. Professional responsibility for the design remains with the engineer of record, so clear agreements on review time, scope and liability are essential.

Progressive design-build

Progressive design-build selects the design-builder primarily on qualifications, then develops design collaboratively with the owner before agreeing a price. If price negotiations fail, the owner can take the design to another contractor. It is growing in water, wastewater and transportation sectors because it combines early collaboration with owner input and price transparency.

The off-ramp provision gives owners leverage, but it also means the design-builder may invest effort without guaranteed construction work. Clear stage definitions, compensation for design phases and transparent cost models help build trust.

Integrated project delivery

IPD uses a multi-party agreement among owner, designer and builder, sharing risk and reward based on project outcomes. It emphasises collaboration, shared incentives and lean practices, and is used mainly on complex private projects such as healthcare. It requires high trust and experienced participants.

IPD contracts often place a portion of each party's profit at risk, paid out based on project outcomes such as cost and schedule targets. Decisions are made by a joint management team, and co-location of the team is common to support collaboration.

Implications for engineers

Delivery model affects who engineers work for, their liability, the level of design detail required, and how design decisions are made. Engineers must understand contract terms, insurance requirements and their role in collaborative processes.

Professional liability insurance and indemnity terms deserve careful review under collaborative models. Shared-risk agreements may include waivers among parties, and engineers should ensure their insurance coverage aligns with contractual obligations.

Collaborative models also demand different skills: working closely with contractors and owners, providing cost and schedule input, and adapting design as decisions evolve. Firms that develop these capabilities are well positioned as alternative delivery grows.

Key takeaways

  • Design-bid-build separates design and construction.
  • CMAR adds contractor input during design.
  • Design-build shifts design risk to the contractor.
  • Progressive design-build combines collaboration with price transparency.
  • Delivery models change engineers' scope, liability and role.

Frequently asked questions

What is progressive design-build?
A design-build approach selecting the team on qualifications and developing design collaboratively before setting price.
Who does the engineer work for in design-build?
Typically the design-builder, often a contractor-led team.
What is IPD?
Integrated project delivery, a multi-party contract sharing risk and reward among owner, designer and builder.
Which delivery model is best?
It depends on project complexity, owner capability, risk tolerance, schedule and procurement rules. Many owners evaluate models project by project.

Need an engineer for this kind of work?

Describe your project and we will match you with licensed firms that specialise in construction engineering.

EngineerMint Insights are editorial briefings, not engineering advice. Verify with a licensed engineer before applying to a specific project.